How to
Build a House in Southern Woods
While it is true
that you do not need to get all of the inspections and
permits to build in Southern Woods
that one would have to acquire to build in Austin, there
are permits and a process to go through.
1)
Plans
Building begins with a complete set of building plans
"signed and sealed for construction." Your builder
needs several sets to be able to give you a bottom line
price on the house.
The Architectural Control Committee (ACC) of the Homeowners
Association of Southern Woods, Inc.
(HOA) will need to see a full set of plans signed and
sealed for construction that has the total square footage
and details concerning the exterior façade and roof
materials before approval can be made.
The house dimensions (2000+ sq. feet) and materials (at
least 50% masonry exterior) must comply with
the deed restrictions before approval.
A survey of the property showing the approximate location
of the foundation is also required (50 foot set
backs from property lines.)
Once approved, the ACC will return your plans with a letter
to pass along to your lender.
2)
Utilities
Electricity
The Pedernales Electric
Cooperative provides electrical service.
To have electricity on your lot, you must first become a
member. The closest office is at 11940 Manchaca
Road - (512) 219-2602. This office is located less than a
1/4 mile north of intersection of RR1626 and
Manchaca Road on the west side of road.
Establishing your electrical account is easy - it’s just a
matter of paper work and a check for $675.00.
Having electrical service installed will take 6 to 8 weeks.
It would be prudent to make this one of the first
things you accomplish.
Telephone
Verizon provides telephone
service. They can be reached at 1-800-483-4400.
Time Warner also provides Voice Over Internet (VOP) phone
service as well.
Cable TV
Time Warner provides cable service. They also offer
Roadrunner Internet high-speed service as well.
Time Warner can be reached at 512 485-6000.
Gas
Gas appliances need a propane
service. Several companies are listed in the yellow pages.
Most of the
companies will either sell or lease you a tank. Placement
of the tank above or below grade is a matter of
personal choice. Ask for the form to send to the Texas
Railroad Commission - each gas appliance will
receive a $50.00 rebate.
Water
We are on private wells. Most
wells are 375 to 425 feet deep and the water is from the
Edward's Acquifer.
Wells have been costing between $6,000.00 to as much as
$8,000.00.
Well drilling companies used thus far are: David McDearmon,
Associated, and B&B. Their numbers are in
the Yellow Pages.
The Well Drilling Permit must be obtained from the Barton
Springs/ Edward's Acquifer Conservation
District (BSEACD) Office at 1124-A Regal Row (512)
282-8441. They are located just north of the
Pedernales Electric Cooperative Office off of Manchaca
Road.
If your drilling contractor will turn in his "drill logs"
to BSEACD, they will refund part of your permit fee.
Wastewater
Each lot must have a septic system installed. A large
number of contractors can do the work. A
conventional system with a septic tank and drain field can
cost as much as $10,000.00 or more. An aerobic
system can cost as little as $6,000.00 but must be
maintained by a licensed professional.
A Waste Water Permit is required by the Hays County
Environmental Department. (Permits can be
obtained at Hays County Environmental Office, 1251 Civic
Center Loop, San Marcos, Texas 78666 - (512)
393-2160.). A copy of the wastewater permit must be
submitted with your house plans to the ACC for
approval.
Trash Collection
Weekly trash collection is required. Burning of household
waste is prohibited. Texas Disposal System and
IES pick up each Wednesday.
3)
Permits
Hays County requires a building Permit ($35.00) Before
issuing a building permit, they must first see a set
of plans, signed and sealed for construction.
The ACC needs to see a copy of your building permit along
with the house plans.
Since the HOA owns the roadways of Southern Woods, no
county permit is required now for a driveway.
Before starting construction on the required, a paved
driveway apron on any drive fronting either Southern
Drive or Westway Drive, ACC approval is required. An
18-inch culvert pipe is required.
The lots, which front onto 1626 must share the road cut
already installed by the developer. These cuts were
required by the Texas Department of Transportation (TX DOT)
and cannot be changed without the
permission of TX DOT.
Once the permits have been obtained, copies must be
forwarded to the ACC.
Once plans are finalized, permits obtained, and ACC
approval is granted, the builder is given 12 months to
complete the house. Houses built thus far have taken as
little as 120 days to complete.
It would be wise to get a builder who will commit to a
deadline to minimize the length of time you're
paying interest on a construction loan.
Get your electrical service first, drill the well second
(the well must have electricity to work,) and then your
contractor can begin building. (Without electricity and
water, pouring the foundation and setting the septic
tanks are difficult if not impossible.)
4) Contractor
Requirements
We ask that all contractors
and their sub-contractors park completely on the property
and NOT on the
right-of-way (ROW) owned by the HOA. Maintaining the ROW is
a necessary part of road maintenance.
All concrete trucks are asked to do their wash outs
completely on the property under construction. Concrete
wash outs on the ROW are prohibited and the lot owner will
be fined if this occurs. Cleanup costs will be
assessed the lot owner.